Contractor: ARAD CONSTRUCTION ESTABLISHMENT
Project Summary: The project contributes to serving (376) properties in Block 1038 in Sadad Area through the construction of main sewer lines using the (trench excavation) method, with a total length of 3.8 km, and secondary sewer lines with a total length of 5 km, in addition to the construction of main and secondary manholes with a total number of 521.