PALACE AVENUE JUNCTION - SH DUAJ AVENUE
 
Contractor: Mohsen Haji Group
Cost: BD 334,625
 
Brief Description: The improvement of Shaikh Duaij Avenue/Palace Avenue junction is the last in a string of projects designed to replace roundabouts in Manama with traffic signals. This came following a study prepared by the Ministry of Works; highlighting the fact that roundabouts are no longer capable of handling the increasing traffic.
 
The project comprised replacing the roundabout with a traffic signal, re-constructing parts of Sh. Duaij Avenue and Palace Avenue, in addition to constructing a rainwater drainage network, lighting network and replacing a number of service networks.
Sector : Roads Area : Capital
Project Size : Project Time Frame :
Start Date : 17/06/2012 End Date : 2/12/2012
Project Status : Finished Projects