Trunking is to be manufactured from either mild steel or PVC and shall confirm to BS EN
50085: Part 1, BS EN 50085: Part 2-1, BS 4678: Part 4 and BS 4678: Part 2. Cable trays
shall be manufactured from mild steel. Mild steel trunking and cable trays shall be hot dip
galvanised. Where the trunking or cable trays are cut, drilled or where the galvanising is damaged in
any way the surfaces shall be adequately treated to restore them to the original
galvanised standard. The number of cables installed in the trunking shall not exceed that
recommended in BS 7671 (IEE Regulations), and the resulting space factor shall not
exceed 45%.
The fixing of trunking and cable trays and the installation of cables into or on trunking and
cable trays shall be carried out using the manufacturer's approved accessories and
fixings only. Such accessories and fixings shall be either manufactured from non-
corrodible materials or supplied suitably coated to render them non-corrodible.
3.3.5. Conduit Systems
Conduits for occupied areas to be concealed; conduit for unoccupied areas to be surface
mounted and GS conduit pipe for Plant-Rooms.
Conduits within buildings and structures shall be extra-super-high-impact heavy-gauge
PVC-u conduit, installed with solvent welded joints and shall be installed with screwed
fittings. Conduit systems shall conform to BS 4607: Part 1, BS 4607: Part 5, BS EN 61386: Part-
1, BS 4568: Part 1 as appropriate, and the number of cables installed shall not exceed
those recommended in BS 7671 (IEE Regulations).
The conduit system where it passes through the building structural expansion joints,
suitably rated/sized expansion couplers shall be used in order to absorb the
expansion/contraction. Fixings and accessories associated with conduit systems shall be either manufactured
from non-corrodible materials or suitably coated to render them non-corrodible. No
conduit shall be smaller than 20 mm diameter.
Cable runs shall be continuous throughout. Jointing shall not be carried out in conduits or
at drawing points under any circumstances.
Draw-in boxes shall be spaced so that there is not more than two solid bends, or their
equivalent, or more than nine metres of straight run between draw-in boxes.
Flexible conduit for connection to mechanical equipment.
3.3.6. Cables Laid Directly in Ground
The Contractor shall be responsible for all work associated with cabling including
trenching, ducting under roadways and backfilling of trenches.
Cables shall be laid at a depth of not less than 500 mm or not more than 1,000 mm below
the surface of the ground.
The bottom of the trench and the first 250 mm of backfill shall be fine sand free of stones
or other sharp objects.
Where cable trenches pass through stone fill, the cable shall be laid on an 80 mm bed of
sand. After laying, the cable shall be covered by a further layer of sand to a depth of
80 mm above the top of the cable. Where sand is likely to leach away, a suitable
membrane shall be fitted.
Page 85