1
PART 1 MATERIALS
1.1 General Requirements
The Contractor shall supply all necessary plant, labour, materials and equipment required for
the completion of the Soft Landscape Works. Sufficient labour shall be provided at all times
to complete the works to the Programme and the quality expected.
The Contractor shall provide sufficient personnel and equipment to perform all work in a
professional and workmanlike manner to the satisfaction of the Engineer and in keeping with
horticultural best practice and techniques. The Contractor shall supply a list of personnel for
the Contract from managerial level, to supervise site foremen and general operatives. Staff
must be able to prove their skills in horticulture and have worked in arid environments with
experience of the implementation and maintenance of soft landscape Contracts. A close
working relationship must be established with the irrigation personnel to co-ordinate the
installation, scheduling and maintenance requirements of the irrigation system.
Before the commencement of any work, the Contractor shall check and verify all dimensions
and the condition of areas to be planted and shall inform the Engineer of any discrepancies
between the drawings and/or Specifications and actual conditions. No work shall be
undertaken in any area where there are discrepancies or where conditions are unsuitable for
planting, until approval has been obtained from the Engineer.
The whole of the works shall be executed in a safe, orderly and workmanlike manner to the
satisfaction of the Engineer and the Employer. Any work rejected as a result of non-
compliance with the Specification shall be removed and replaced at the Contractor's
expense. The Contractor shall clear away all unused materials and waste as the work proceeds and
upon completion.
The quantities of plants – trees, palms, shrubs, groundcover and grassed areas – as detailed
in the contract documents shall be checked by the Contractor. The Contractor shall be
responsible for the correct ordering of items and their setting out on site.
The Contractor shall be responsible for ensuring that the numbers of plants - trees, palms,
shrubs, groundcover and grass areas - at final handover of the works, are as detailed on the
Drawings, or as otherwise agreed with the Engineer on site.
The Contractor must consult and co-ordinate with all the relevant public utility authorities
before the commencement of excavations and confirm the exact line and location of all
service runs. All services shown on the Landscape Drawings should be treated as a ‘guide’
only and should under no circumstances be considered as accurate. Any damage to services
during excavation, soiling or planting operations shall be the total responsibility of the
Contractor. 1.2
Inspections All inspections shall be undertaken by the Engineer. The Contractor shall request inspection
at least two (2) weeks in advance of the time the inspection is required.
Inspections will be required for the following stages of work:
• •
• •
• •
At the time of planting bed/medium preparation
During final grading and soil preparation
Plant material after delivery to site and prior to planting
As trees are marked and set out for planting prior to excavation of tree pits
During installation of irrigation and at completion
As tree pits are excavated prior to backfilling
Page 7