SANITARY PROJECT IN A’ALI BLOCKS 746 AND 748

Cost: BD1,585,188

Contractor: Jalal Al A'Ali Contracting

Summary:

Work comprises of expanding the current sewerage network by implementing 7.6km long main connections and 3.2km long sub-connections, in addition to 2 lifting stations and connecting 380 houses in Blocks 746 & 748 to the network in A'Ali. ​

Sector : Sanitary Area : Central
Project Size : Project Time Frame :
Start Date : End Date :
Project Status : Finished Projects