Shaikh Khalifa Sports City at Isa Town

 

Project description:

The Project is constructed at Isa  Town Sports Stadium site with a total area of 80,000 m2 and composed of a main grandstand with a capacity of 3600 spectators, multipurpose sports hall with a capacity of 3600 spectators and swimming hall including two pools for lapping and diving with a capacity of 500 spectators in addition to the associated external works,services and parking areas. It will also include later resurfacing of the existing running track, replacing the artificial turf with natural grass  and upgrading of existing perimeter football seating and lighting system.

The project’s Consultants are M/s Tilke and Partners WLL. The main construction works were awarded to M/s Mohammed Jalal Contracting and the total construction cost was BD 9, 212, 230/-.

The main construction works are completed and the Completion Certificate for the project is being issued to the Contractor. The project which is intended to promote sports in the Kingdom of Bahrain was constructed according to the latest international standards.

  

  

Sector : Strategic Area : Central
Project Size :   Project Time Frame :  
Start Date : 12/05/2008 End Date : 12/05/2013
Project Status : In Progress Projects